APPLICATION: ARC WELDING
A wheelchair manufacturer stumbled across a problem while in the
midst of introducing his new line of lightweight steel and aluminum
wheelchairs. There were eight workers assigned to the job of brazing
all of the frame components for these products. In the first year, production
rates reached 2,500 wheelchairs, leading plant management
to the conclusion that the current project team was unable to keep up
without hiring additional workers.
The company had a large goal in mind, and it didn't take long for them to realize that they needed to find a better method to meet these production goals. With this dilemma looming large, the wheelchair manufacturer enlisted the help of Fanuc Robotics, in particular, their robotic arc welding.
The company needed a robot to weld small diameter tubing with wall thickness of 0.049 in. to 0.065 in. Additionally, the robot welders would also be required to turn tight corners when welding chair joints.
Fanuc Robotics worked together with Lincoln Electric developing a robotic arc welding system to weld mild-steel wheelchair side frames and foot rests. The integrated companies' solution included robots, tooling, welding equipment, software and system integration.
THREE ROBOTS DO THE JOB OF 45 WORKERS
Fanuc and Lincoln Electric's teamwork allowed the wheelchair
manufacturer to be the first to robotically weld all frame
components. Growing on that success, they currently have three
robotic arc welding cells and plan to install a fourth.
In order to meet the production goal of 45,000 wheelchairs, the company would need to have 45 brazers working two shifts. With that amount of labor content, they would have had a difficult time sustaining profit.
SYSTEM DESCRIPTION
The solution to the wheelchair challenge came in the form
of three robotic welding cells using: a FANUC Robotics ARC
Mate 100 robot; Lincoln NA-5R control and wire drive; a Lincoln
Idealarc CV-400 power supply; part-specific tooling and FANUC
ArcTool application software. Two cells produce side frames of
six components and subassemblies, and foot rests. The third
weld cell welds two side frames and foot rest assemblies, completing
the wheelchair structure.
WORKERS RETRAINED TO OPERATE ROBOTS
The employees who started this project by manually brazing
the wheelchair frames finished this project after training, during
system operation. The manual brazers were trained to operate
and maintain the robotic system. Following tooling setup, an
operator is responsible for loading a fixture onto a 180° turntable
positioner. The two-station positioner allows the operator
to load parts and to remove welded assemblies while the robot
begins work on a second assembly.
Once welding is complete, the operator inspects each weld for cosmetic quality. As a final measure for ensuring structural quality, the company performs destructive tests three times per day.
SYSTEM BENEFITS
Since the installation of these robotic welding cells, weld
reject is less than 1%, and require only manual touch-up at a
manual brazing station. Cosmetic quality has also been significantly
increased.
Production rates have taken a turn for the better, seeing much improvement. Manual brazing of wheelchair frames took as long as 45 minutes. Robotic welding has reduced frame production time to a mere 3 minutes.
APPLICATION: MATERIAL REMOVAL
The challenge of improving the finishing process of femoral
orthopedic implants was brought in front of an orthopedic implant
manufacturer. The company's current manual finishing
process raised concerns with production time, material waste
and rework costs.
M-16iB robotic femoral implant polishing system.
ACME Manufacturing Company, Auburn Hills, MI, stepped up to the plate with what they believed was just the solution the manufacturer was looking for. ACME's plan was to implement a robotic finishing system that utilized a FANUC Robotics' M-16i R-J3 robot to emulate the movement of manual polishing orthopedic implant devices.
The M-16i RJ-3 robot provides the necessary movement, strength and reliability that they need. ACME and FANUC Robotics did a great job of integrating a robotic system that has led to a predictable manufacturing process for their company.
SYSTEM DESCRIPTION
The problem solver, FANUC's 35-pound,
6-axis robot, works with four ACME-designed
and built finishing heads to metal
finish an orthopedic implant in one continuous
step. Specialized tooling orients, fixtures
and polishes a single component to
within a ± 0.005-in. tolerance. ACME is the
proud developer of these tools. A touch
screen operator interface panel enables
the machine operator to create, retrieve
and change part programs.
ACME's application software uses human- like brainpower to store and manage all part files. On top of that, a set of user- friendly manuals and engineering documents are stored on the personal computer for easy operator access. ACME has designed off-line troubleshooting capabilities by using a modem connection. ACME's modem connection allows the company to upgrade application software or modify the system operations from a remote connection.
ROBOTS INSTALLED
Following the design, build and integration
of the ACME robotic cell, the unit is
shipped to the customer as a single module.
The majority of these cells are installed
at a user's facility and are up and ready to
get to work within two business days.
SYSTEM BENEFITS
ACME's robotic cell offers its users a
number of cost-saving benefits. The polishing
time of an orthopedic implant device
can be significantly reduced from 30
minutes to 12 minutes. These robotic systems
nearly eliminate scrap and rework,
and perishable costs are substantially
reduced. Compared to manual finishing
operations, robotic cells use fewer belts,
buffs, compounds and contact wheels.
Parts can be run in small batches and programs,
while process data can be stored
and retrieved via an Ethernet link.
Explore the April 2007 Issue
Check out more from this issue and find your next story to read.
Latest from Today's Medical Developments
- Collaborate North America 2025
- ModuleWorks' 2024.12 software components
- Stretchable, flexible, recyclable – this plastic is fantastic
- Discuss the upcoming year in manufacturing with GIE Media editors
- TDK Ventures invests in ANYbotics
- Our first webinar of 2025 highlights additive manufacturing
- Costa Rica, a global magnet for medical devices
- PhD student helps develop medical device for children with congenital heart defects